Procurement guide

How to record furniture finish approvals across a project

Keep furniture colour and finish decisions traceable with sample IDs, revision records, written approvals and a clear process for later changes.

Give every finish decision a reference

A message saying ‘the colour is approved’ leaves important questions unanswered: which sample, which material, which revision and which furniture items? For a hotel, showroom or residential project, use a finish register that links each decision to the item schedule and the physical sample being reviewed.

This is a suggested procurement workflow, not a statement that a particular finish, material or production capability is already available. Agree the approval process with the parties responsible for the actual order.

Define what the sample represents

Record the sample ID, supplier, date received, material or substrate, finish reference and revision. State whether it represents a colour direction, a surface texture, a gloss level or a complete finish proposal. List the furniture SKUs, components and drawing revisions to which it is intended to apply.

Ask the supplier to identify the proposed material and finish specification rather than inferring them from a photograph. If the project uses timber, veneer, metal and upholstery together, give each material its own reference and record which combinations need approval as a set.

Agree how the samples will be reviewed

Agree the physical samples, viewing location, lighting conditions and people involved in the review. Use photographs to identify samples and communicate comments, while keeping the agreed physical reference available to the parties who must compare it with later samples or goods.

Define which visible characteristics matter for the project: colour direction, grain selection, surface texture, gloss, edge treatment and coordination between adjacent components. If natural variation is acceptable, ask for the range to be shown and recorded. A single approval should not silently stand for an unspecified range.

Where a project requires measured colour tolerances, a named test method or a performance requirement, agree those separately with an appropriate technical reviewer and supplier. Do not invent a universal tolerance or assume that approving appearance also proves durability or regulatory compliance.

Use explicit approval states

Use clear states such as submitted, comments issued, revise and resubmit, approved for a named purpose, and superseded. Record the approver's name or role, the date, the sample revision and any conditions. Keep a conditional decision separate from an unconditional release.

Distinguish approval of a finish sample from approval of a complete furniture sample and permission to start production. Identify who can authorise each step. If an order contains several finishes or room types, specify exactly which items are released and which remain open.

Keep a register that can be checked at handover

A practical register includes: project and finish ID; material or substrate; sample and drawing revision; applicable SKUs and quantities; date submitted; review status; comments; approver; approval date; reference-sample location; and the record replaced by a later revision. Attach the written decision and labelled photographs without losing the physical sample reference.

Illustrative example only: finish FIN-07, sample revision B, is approved for the exposed frame of chair CH-02 under drawing revision 3. Upholstery FAB-04 remains under review, so the record does not release the complete chair. These identifiers are examples, not ROOMVANO product specifications or an actual customer project.

Treat a later change as a new decision

When a finish, substrate, upholstery or approved combination changes, open a change record. Identify the previous and proposed revisions, affected items, the reason for the change and who must review it. Ask the supplier to confirm any effect on sampling, cost, production sequencing and delivery before accepting a revised plan.

Mark the previous reference as superseded and tell the relevant purchasing, design, supplier and inspection contacts which version now applies. Keep the old record for traceability. A newer photograph in a message thread should not become the production reference without a clear written decision.

Carry the approved reference into sampling and inspection

Before reviewing a furniture sample or shipment, confirm that the reviewers have the same finish register, current drawings and agreed reference samples. Record discrepancies against the specific reference and component, then agree the next action and responsible person.

For a project enquiry, send the item schedule, finish direction, material expectations, destination and sample-approval roles. Explain which decisions are fixed and which need development. This gives the supplier a clearer basis for responding without turning an early visual reference into an unverified promise.